PSNH informational meetings are starting to wind down in Coos and Grafton Counties. Since the earliest sessions in late October and early November, audiences have become increasingly negative and skeptical about the entire process. According to the Valley News, in last night's info meeting in Lebanon concerning the proposed alternate route through the Upper Connecticut valley towns of Haverhill, Piermont, Orford, and Dorchester, "environmentalists and land owners . . . reacted with dismay." Haverhill Town Manager Glenn English called the Northern Pass a "blight" that's going to have "no direct benefit" to the North Country. Despite PSNH's rhetoric of inclusion and "input," English feels that local communities will have little actual role in decision making once the regulatory merry-go-round starts up. Orford resident Sally Tomlinson commented that it almost looks like "games" are being played in attempting to pit preferred and alternate routes--and towns--against one another.
Faith in the process is now so low that no one was likely to believe PSNH spokesperson Allison McLean last night when she claimed that "we're kind of at step one of a marathon here." That talking point was echoed this morning on NHPR when PSNH's Martin Murray insisted that there's plenty of time for public "input" since we're only at mile three of a marathon. Few people are lulled into complacency by this talking point. Most of us realize that we're at the eleventh hour in terms of PSNH's efforts to capture the one thing that it must have to bypass public opposition, eminent domain. If PSNH has not already done so, it will likely soon make an end run around public opposition by getting a purchase agreement for some nominal amount of power from Hydro-Quebec, thereby claiming that it is a public utility not a private merchant transmission line. The next step would be to apply to the NH Public Utilities Commission for public utility status and thereby garner the privilege of taking our land by eminent domain.
At another meeting last night, one organized by and for the opposition in North Woodstock, Ray D'Amante came up from Concord to express solidarity with the North Country and to reiterate that it's the eleventh hour. Anyone who thinks that we are only at McLean's step one or Murray's mile three will be left in the starting blocks as PSNH crosses the finish line and the North Country's fate is sealed.
How do you get in the race to save the North Country? Write to your elected officials, to Senator Gallus, Governor Lynch, Senator Shaheen. Persist. Tom Mullen wrote to Senator Gallus on January 20 and again on January 21. With Tom, don't settle for "no position" as an answer from the people we elect to exercise leadership on our behalf.
Contact info for Grafton County elected officials is here.
Contact info for Coos County elected officials is here.
Bury the Northern Pass, a group of concerned citizens in Grafton County, participates in the No Northern Pass Coalition. To join the email list, write to burynorthernpass@gmail.com.
Sunday, January 23, 2011
Northern Pass's Monthly Allowance for December 2010: $1,093,080.00
A look at how much Hydro-Quebec is spending on developing the Northern Pass project right now.
How much did you earn last month? Never mind, you'd probably rather not think about it these days. Per capita monthly income in Coos County in 1999, the latest U.S. census data available, was $1,435. Median monthly household income in Coos in 2008 was $3,566, under $900 per week.
How much did the Northern Pass spend on development in December 2010 alone? $1,093,080. Over a million dollars in a single month! $200,000 went for legal; $72,000 for environmental; $465,00 for routing analysis and preliminary engineering; $50,000 for real estate services; $25,000 for corporate communications and community outreach; $62,200 for miscellaneous; $224,100 for NPT labor.
The PSNH folks running all over the North Country holding meetings in December to inform us about the power line were probably billed under "NPT labor." The people knocking on our doors wanting us to sign ROE agreements were "real estate services." The new "community relations specialist" was actually a "real estate service," but he was probably billed under NPT labor too.What were those Northern Pass lawyers doing to bill $10,000 a day in December? I wonder how much the Northern Pass blogger earned last month.
Northern Pass's December 2010 development spending is just the tip of the iceberg. Between January 2009 and March 2011, development costs will total $16M. And that's a tiny fraction of the overall cost of the project, $1.2B.
Who's really footing the bill for all this spending to push an HVDC power line through New Hampshire? Hydro-Quebec, ultimately, the province of Quebec. PSNH is merely the face of the project we meet in our town hall meetings and at our front doors; Hydro-Quebec silently bankrolls it. Buried in the middle of the massive Transmission Service Agreement (TSA) that Northern Pass has publicly filed with the Federal Energy Regulatory Agency (FERC) is the agreement letter that spells it out.
So, while your household was struggling to get by on under $900 per week (2008 Coos median), Northern Pass was allowed to spend $273,000 a week in December. Apples and oranges? Yes. But have no doubt that the more Northern Pass gets to spend on developing the power line project, the greater the danger that your household in northern New Hampshire will have to get along on even less in the future. To quote Deb Reynolds, District 2 state Senator 2006-2010, "the Hydro Quebec/Northern Pass project will ultimately serve to drive the nail in the coffin of what is left of the economy of the North Country."
A company with the vast financial resources of Hydro-Quebec has the money to bury the line if it wants to ship its power down to the greater Boston area through New Hampshire. Could it be any clearer? New York State figured it out. New Hampshire has too.
Bury the Northern Pass, a group of concerned citizens in Grafton County, belongs to the No Northern Pass Coalition. To join the email list, write to burynorthernpass@gmail.com.
How much did you earn last month? Never mind, you'd probably rather not think about it these days. Per capita monthly income in Coos County in 1999, the latest U.S. census data available, was $1,435. Median monthly household income in Coos in 2008 was $3,566, under $900 per week.
How much did the Northern Pass spend on development in December 2010 alone? $1,093,080. Over a million dollars in a single month! $200,000 went for legal; $72,000 for environmental; $465,00 for routing analysis and preliminary engineering; $50,000 for real estate services; $25,000 for corporate communications and community outreach; $62,200 for miscellaneous; $224,100 for NPT labor.
The PSNH folks running all over the North Country holding meetings in December to inform us about the power line were probably billed under "NPT labor." The people knocking on our doors wanting us to sign ROE agreements were "real estate services." The new "community relations specialist" was actually a "real estate service," but he was probably billed under NPT labor too.What were those Northern Pass lawyers doing to bill $10,000 a day in December? I wonder how much the Northern Pass blogger earned last month.
Northern Pass's December 2010 development spending is just the tip of the iceberg. Between January 2009 and March 2011, development costs will total $16M. And that's a tiny fraction of the overall cost of the project, $1.2B.
Who's really footing the bill for all this spending to push an HVDC power line through New Hampshire? Hydro-Quebec, ultimately, the province of Quebec. PSNH is merely the face of the project we meet in our town hall meetings and at our front doors; Hydro-Quebec silently bankrolls it. Buried in the middle of the massive Transmission Service Agreement (TSA) that Northern Pass has publicly filed with the Federal Energy Regulatory Agency (FERC) is the agreement letter that spells it out.
So, while your household was struggling to get by on under $900 per week (2008 Coos median), Northern Pass was allowed to spend $273,000 a week in December. Apples and oranges? Yes. But have no doubt that the more Northern Pass gets to spend on developing the power line project, the greater the danger that your household in northern New Hampshire will have to get along on even less in the future. To quote Deb Reynolds, District 2 state Senator 2006-2010, "the Hydro Quebec/Northern Pass project will ultimately serve to drive the nail in the coffin of what is left of the economy of the North Country."
A company with the vast financial resources of Hydro-Quebec has the money to bury the line if it wants to ship its power down to the greater Boston area through New Hampshire. Could it be any clearer? New York State figured it out. New Hampshire has too.
Bury the Northern Pass, a group of concerned citizens in Grafton County, belongs to the No Northern Pass Coalition. To join the email list, write to burynorthernpass@gmail.com.
Friday, January 21, 2011
The Southern Pass?
Today's Concord Monitor carries an article by Tara Ballenger concerning the 28 miles of new right-of-way that the Northern Pass may have to cut in the Concord NH area.
Scope of impact depends on FAA
The Northern Pass project by Northeast Utilities and Hydro Quebec might require cutting as much as 28 miles of new right of way in the southern half of the state. How much - if any - hinges largely on the project getting approval from the Federal Aviation Administration to build the towers next to existing lines around Concord's airport, according to Northeast Utilities.
Officials and residents in Concord and neighboring towns are saying they aren't necessarily opposed to the project, which would bring 1,200 megawatts of electricity through 140 miles of high-voltage power lines from Canada to a converter station in Franklin, and then to Deerfield to be piped into the regional power grid. But those who are in the path of the proposed routes are voicing their concerns about clearing new rights of way to build them.
Worries about how transmission lines would affect property values, scenic views and the environment, echo sentiments heard in the North Country, where the proposal of 40 new miles of right of way has sparked significant protest.
"I'm not happy with it at all. I spent my life getting this chunk of land together, and it wasn't to give them a route to run their power lines though," said James Haggett of Pembroke.
Haggett and his wife, Linda, attended a selectmen's meeting in the town Monday. At the meeting, representatives from the project explained that if the FAA doesn't grant Northeast Utilities permission to build towers, which would range in height from 90 to 135 feet, near existing lines around Concord Municipal Airport, a swath of land just over 8 miles long and 150 feet wide may need to be cut through Concord, Pembroke and Chichester to avoid the airport.
"We're waiting for them to give us the determination so we can move forward," said Brian Bosse, project manager for the Northern Pass project, which submitted an application in late October.
Representatives for the project told people at the Pembroke meeting that they hope to hear back from the FAA in the coming weeks, said Martin Murray, spokesman for Public Service of New Hampshire, which is owned by Northeast Utilities. He said his estimate is based on how long the FAA has taken to make decisions about obstructions near airports in the past.
"We're as eager as the residents to find out," said Murray, who added that Northeast Utilities prefers to use the existing right of way by the airport if it's possible. "But I can't tell you what they're going to do."
The lines in the current right of way around Concord - including the lines around the airport - vary in height from 48 to 88 feet, so the new towers, which would be built next to the old ones, may represent a considerable increase in height.
No one at the FAA could address the specifics of the project's application for approval, but a spokesperson said that if the plans involve building towers high enough and close enough to the runway, aircraft will have to alter angles or directions to land safely and the approval process will involve significant research as well as the input of several arms of the administration.
The eight miles of new right of way would cut through undeveloped private land in the Broken Ground area of Concord north of Route 393 in Concord, and in north Pembroke and south Chichester between Plausawa and Garvin Hills. It would cut through 54 separate land parcels, most of them residential, Murray said.
"It's going to be a massive scar across the entire face of that mountain, which is very visible from the west looking east," said Raymond D'Amante, referencing the impact to the hills. D'Amante is a Concord-based attorney who will represent several Penacook and Chichester residents in upcoming Department of Energy hearings about the project and other meetings.
"More important is the impact on the properties that will be taken as well as the hundreds of properties that will not be taken but will still have the towers in their yards or just beyond their yards. They are massive steel towers" that are well over twice as high as the normal wood power lines people are used to seeing in that area," he said, adding that several historic properties, including homesteads dating to the 1700s in Chichester, will be affected.
Read the remainder of the article and see the route map here.
Bury the Northern Pass, a group of concerned citizens in Grafton County, is a member of the No Northern Pass Coalition; to join the email list, write to burynorthernpass@gmail.com.
Power plan has local connection
By Tara Ballenger
Created 01/21/2011 - 00:00
Concord Monitor
Scope of impact depends on FAA
The Northern Pass project by Northeast Utilities and Hydro Quebec might require cutting as much as 28 miles of new right of way in the southern half of the state. How much - if any - hinges largely on the project getting approval from the Federal Aviation Administration to build the towers next to existing lines around Concord's airport, according to Northeast Utilities.
Officials and residents in Concord and neighboring towns are saying they aren't necessarily opposed to the project, which would bring 1,200 megawatts of electricity through 140 miles of high-voltage power lines from Canada to a converter station in Franklin, and then to Deerfield to be piped into the regional power grid. But those who are in the path of the proposed routes are voicing their concerns about clearing new rights of way to build them.
Worries about how transmission lines would affect property values, scenic views and the environment, echo sentiments heard in the North Country, where the proposal of 40 new miles of right of way has sparked significant protest.
"I'm not happy with it at all. I spent my life getting this chunk of land together, and it wasn't to give them a route to run their power lines though," said James Haggett of Pembroke.
Haggett and his wife, Linda, attended a selectmen's meeting in the town Monday. At the meeting, representatives from the project explained that if the FAA doesn't grant Northeast Utilities permission to build towers, which would range in height from 90 to 135 feet, near existing lines around Concord Municipal Airport, a swath of land just over 8 miles long and 150 feet wide may need to be cut through Concord, Pembroke and Chichester to avoid the airport.
"We're waiting for them to give us the determination so we can move forward," said Brian Bosse, project manager for the Northern Pass project, which submitted an application in late October.
Representatives for the project told people at the Pembroke meeting that they hope to hear back from the FAA in the coming weeks, said Martin Murray, spokesman for Public Service of New Hampshire, which is owned by Northeast Utilities. He said his estimate is based on how long the FAA has taken to make decisions about obstructions near airports in the past.
"We're as eager as the residents to find out," said Murray, who added that Northeast Utilities prefers to use the existing right of way by the airport if it's possible. "But I can't tell you what they're going to do."
The lines in the current right of way around Concord - including the lines around the airport - vary in height from 48 to 88 feet, so the new towers, which would be built next to the old ones, may represent a considerable increase in height.
No one at the FAA could address the specifics of the project's application for approval, but a spokesperson said that if the plans involve building towers high enough and close enough to the runway, aircraft will have to alter angles or directions to land safely and the approval process will involve significant research as well as the input of several arms of the administration.
The eight miles of new right of way would cut through undeveloped private land in the Broken Ground area of Concord north of Route 393 in Concord, and in north Pembroke and south Chichester between Plausawa and Garvin Hills. It would cut through 54 separate land parcels, most of them residential, Murray said.
"It's going to be a massive scar across the entire face of that mountain, which is very visible from the west looking east," said Raymond D'Amante, referencing the impact to the hills. D'Amante is a Concord-based attorney who will represent several Penacook and Chichester residents in upcoming Department of Energy hearings about the project and other meetings.
"More important is the impact on the properties that will be taken as well as the hundreds of properties that will not be taken but will still have the towers in their yards or just beyond their yards. They are massive steel towers" that are well over twice as high as the normal wood power lines people are used to seeing in that area," he said, adding that several historic properties, including homesteads dating to the 1700s in Chichester, will be affected.
Read the remainder of the article and see the route map here.
Bury the Northern Pass, a group of concerned citizens in Grafton County, is a member of the No Northern Pass Coalition; to join the email list, write to burynorthernpass@gmail.com.
Labels:
Concord,
eminent domain,
historic properties,
property values,
right of way,
route,
towers
Subscribe to:
Posts (Atom)