Excerpts on Northern Pass from Northeast Utilities investor conference, July 30, 2013. Full transcript is at seekingalpha.com
"And we are doing this as really kind of good citizens, good
stewards of the state . . . as we always have and everything PSNH
has ever done inside of New Hampshire."--Thomas J. May, CEO & Pres.
NU’s Q2 investor call
– July 30, 2013
Northern Pass
excerpts
As most of you know, we had some
very important news on June 27. We announced a new route for the northernmost
40-mile section of our Northern Pass transmission project. We had been working
on a new route for more than 2 years and we were thrilled to be able to
announce it in New Hampshire 5 weeks ago. The Northern Pass team did a
tremendous job putting together a proposal that accommodates the concerns of
many in the state's north country, while also delivering very significant
economic and environmental benefits that are core to this innovative project.
This northernmost section of the new
route has about 32 miles of overhead line on new rights of way that we either
own or have under lease and approximately 8 miles of underground. As result of
the underground work and other changes to the structure configuration, we have
raised the project's cost estimate to $1.4 billion. The new preferred route
addresses many of the concerns that have been raised about the project. The 2
underground sections, lower structures and heights and a route that takes the
project well to the East of our earlier route. We have significantly reduced
the project potential visual impact.
Additionally, the number of
properties that would have overhead lines has been reduced to 31 from 186.
Areas with new overhead lines are now located in generally more remote terrain
and use natural topography to help with visual screening. On July 1, we filed
an amended application with the U.S. Department of Energy and there is now a
link to that filing on the Northern Pass website. We expect the DOE to hold
scoping meetings this fall. These scoping meetings will offer the public the
opportunity to comment on the project and will be an addition to our own open
house forums. Our open houses begin next week in the northernmost area of the
project and eventually, will cover towns all along the route.
The public will be able to meet
face-to-face with project representatives and view maps and other information
specific to their community. The DOE will now continue to work on the draft
environmental impact statement for the project. As soon as that draft is
complete, we will use it as part of our siting application with the New
Hampshire site evaluation committee. Once we file that application, the site
evaluation committee will review and adjudicate it. Our plan has both the state
and federal permitting processes complete by mid-2015.
On that schedule, we expect to bring
the project into service around mid-2017. The benefits of the Northern Pass and
this 1,200 megawatts of firm capacity remain extraordinarily persuasive. We
expect the project will lower New England energy cost by $200 million to $300
million annually, between $20 million and $35 million, of which will directly
accrue to New Hampshire customers. Because Hydro-Québec is almost exclusively a
hydroelectric system, it is expected to reduce the region's carbon dioxide
emissions by up to 5 million tonnes per year. We expect the project will
increase property tax revenue in New Hampshire, in the project host
communities, by about $28 million per year.
Effective Thursday, August 1, Gary
Long will move from his long time position as President of PSNH, to work
fulltime on the Northern Pass and other New Hampshire renewable energy
initiatives. Larry* has done an excellent job over the past 13 years leading
PSNH through industry restructuring and through some major initiatives such as
the innovative conversion of our Shiloh 5 [ph] unit from a coal boiler to a
renewable biomass generator. As one of the most respected business leaders in
New Hampshire, Gary will play a key role in ensuring that the benefits of the
Northern Pass project are delivered to New Hampshire residents.
. . . . . . . . . . . .
Q&A
Okay, very good. And a question for
Lee. Lee, is there any public feedback in the newspapers, politicians comments,
et cetera, on the new route for Northern Pass?
Yes, I would say, Kit, by and large,
it has been very positive. I think the fact that seeing essentially 8 miles of
underground -- particularly 8 miles of underground around very sensitive areas,
environmentally sensitive areas, has all been very positive. I think that the
real sense is that this company essentially took a hiatus of 2 years to come up
with a route that is more sensitive to the environment, to the folks that live
along the route, to the citizens of New Hampshire and that's being paid a lot
of very positive compliments. We received a number of editorials in newspapers
that's in support of the project, particularly because as folks look around to
New England energy capacity situation and see anywhere from late 9,000 of old
retired plants or plants that will have to retire rather, and they have, in
many cases, questionable reliability. They know there's a need for this. This
is clearly the best project for the region or they will be the best project for
the region in the next 50 or 60 years in terms of its firm power, clean power
and reliable power. So we see a building consensus in the polls that were
taken, we see a rise in support for the project.
I wanted to start with a couple of
questions for Lee on Northern Pass, specifically around the timing of
approvals. I believe you said you're excepting processes to be done by mid '15,
which is about 24 months from now. If we work backwards a little bit, the New
Hampshire State Evalution Committee takes about 8 months. And before that,
you'll need to get the draft approval from the DOE. If the DOE scoping meetings
don't start until this fall, that only leaves about a year maybe, even less,
for the DOE draft decision. Does that seem realistic to you? How confident are
you in that mid '15 timing to end the approval process?
Yes, I mean at this point in time,
based on everything we know, we're still confident. So if you think about the
scoping meetings, the scoping meetings are really all about the DOE coming into
the impacted communities, and it will probably be a kind of a northern part of
the state midsection towards the southern part of the state to probably be --
whatever, 4, 5 meetings. And it's really the opportunity for the DOE to hear
from the people in those communities, to take their input into the overall
impact of the line, but the real hard work is really all done around through in
the environmental assessment. These are essentially environmental scientist who
are out in the field taking samples and so forth. So you get the feedback, you
get all the environmental samples, the data, you do the analysis, you factor in
the comments of the public, and the DOE makes the decision. So right now, I
would say, we think that, that is still a realistic timeframe.
Okay. Now the community outreach
you've done in the past few months and the open houses you will be doing in the
coming months, will that in any way, help speed along the DOE approval? Or the
site evaluation committee? Or is that independent, just trying to gain support
and the best approach for you guys to take.
Thomas J. May - Chief Executive Officer, President, Trustee and Member of
Executive Committee
Yes, they're really quite
independent, the DOE is, by their nature, completely independent, and will
conduct its own analysis and studies in accordance with their procedures and
requirements. And we are doing this as really kind of good citizens, good
stewards of the state, of the committee, as we always have and everything PSNH
has ever done inside of New Hampshire. So this is really all about creating
better understanding in the communities of the value of the project, the impact
of the project. We will have topical overviews or what it would look like if
the lines run through a particular area, we'll be able to see that using kind
of a GIS or global information systems, super imposed transmission lines on
that. So this is really about learning more about the project and building a
greater trust level to the public.
Great. Next question is on, the cost
of the project went up from $1.1 billion to $1.2 billion, and now $1.4 billion.
Given your agreement with Hydro-Québec, how does that affect the earned ROE?
And what you'll be collecting from HQ? Is there any upside to your earnings or
downside to your ROE because of these higher costs related to undergrounding
the line?
Jay S. Buth
- Chief Accounting Officer, Vice President and Controller
Well, in regards to the ROE, the ROE
level is set by contract, so there's no change to the ROE, particularly during
the construction of the project after the project is complete and in service,
the ROE would flow off of the base ROE of the region by a band [ph] of I think
it's 140 basis points, 142 basis points. Now to the extent that the project
costs $200 million more, the equity base has now gone from essentially $600
million to $700 million, so you're earning 12.56 on a higher equity base, so
that would definitely be more earnings for the company. Then you would look up
the increase in that capital to $200 million spaced over 3 years, a $25 million
pick up in 2015, $100 million pick up in 2016 and a $75 million pick up in
2017.
Okay. And then also [indiscernible]**, that editorial about that specific piece of land
and everything, we've -- you know what I'm talking up, with research in
Northern Pass, does this alternative proposal that you have, do you think that
deals with that and that specific sort of crucial area.
Yes, Paul, this is Lee. Yes it does,
actually. The original proposal we had was essentially going under about 100
feet or so, 115 feet of that land underground. So you -- visibly, you would see
nothing on the land that is in conservation. But this new route doesn't go near
there, it goes underground. It goes away from it. So this resolves their issue
that they had in the editorial.
____________________
*Gary.
**Shaheen - Gregg editorial